Foreign investment group Sev.en said a series of catastrophic failures at the Callide power station had led to 1,700 days of lost generation capacity.
Callide C’s Czech co-owner is seeking to recover losses from three disasters at the coal power station, which it says were caused by mismanagement.
Oxyfuel technology has been retrofitted at a 700-MW coal-fired power plant in Queensland, Australia, and is now capturing carbon dioxide from one of the plant’s six steam boilers. The Callide Oxyfuel ...
Czech group Sev.en Global Investments said on Monday it is seeking to reclaim losses of over $1 billion in a lawsuit against joint venture partner Callide Energy Pty Ltd ( ...
The troubled Callide C coal plant has suffered another major incident – described as an “explosion” or a “blast” – that will take one 420 megawatt (MW) unit offline for at least two months, just as ...
The state-owned power company released a summary of an internal technical report on the explosion on Tuesday, outlining the series of failures of the plant’s backup systems and describing the ...
Federal Court judge Roger Derrington on Thursday rejected the application of Deloitte administrator Richard Hughes to allow a meeting of creditors of the collapsed private company that owns half of ...
The Callide C coal generator in Queensland was being operated without the required regulatory approval when one of its units blew up in May, 2021, and nearly crashed the grid. The Australian Energy ...
The successful sale of Callide Mine by Anglo American for an undisclosed amount has garnered attention from the mining industry and been welcomed by the local community. The thermal coal mine near ...